June 5, 2015
Ecologization and renovation of the heating plant in Planá nad Lužnicí: On 3rd June the local Building Authority issued the Final Approval for Use of Phase I of the Ecologization project – it includes 4 gas motor-generators, HRSG boilers, the K4 boiler and the hot-water station. All the mentioned equipment had been successfully operated in the trial operation mode since its completion in September last year till its approval for permanent use on 3rd June this year. The recently completed coal boiler K5 and the desulphurisation unit have been currently operated in the trial operation mode. The burning and desulphurization process has been tuned and the contractors, PSG and Invelt companies, have been eliminating backlogs and minor defects. The construction of the second (and last) coal boiler has proceeded in harmony with the approved schedule. Read more information about the project in Planá nad Lužnicí in section PLANA PROJECT. Photographs from the construction process are available in the PHOTOGALLERY.
The rotor has been removed from the renovated TG3 turbine generator and a new one is to be delivered to Planá by the end of June; the new rotor is currently finalized in the production plant of Siemens in Brno. Various assembly and maintenance works are being performed on auxiliary equipment of the TG3. A new high-pressure steam pipeline compliant with parameters of the new boilers has been constructed now. Photographs from the process of TG3 renovation are available in the PHOTOGALLERY.
During the summer the project of renovation of the heating distribution system in the Silon premises will be completed. At the same time C-Energy is preparing new connection lines to connect the new production and storage hall Compact 3 of the Silon company which is being constructed next to the heating plant.