CURRENT INFORMATON ABOUT PROJECTS EXECUTED BY C-ENERGY BOHEMIA S.R.O.

Ecologization and renovation of the heating plant in Planá nad Lužnicí – in June 2014 all four gas motor-generators were commissioned and tested and subsequently successfully certified for ancillary service MZ5, i.e. 5-minute start-up. Currently works are performed to commission HRSG boilers which will utilize exhaust heat from the motor-generators. The assembly of new ecological boiler K5 was launched in June; large parts of the boiler will be installed through the roof of the boiler house which has been dismantled for that purpose. Read more information about the project in Planá nad Lužnicí in section PLANA PROJECT. Photographs from the construction process are available in the PHOTOGALLERY.

Renovation of the heat distribution system – immediately after the execution of a contract with the Brno company Tenza a.s. works on the first part of the project were launched. Part I of the project comprises the replacement of the steam pipeline supplying companies south of C-Energy (Madeta a.s. and Kostelecké uzeniny a.s.) and a part of the so called “northern branch”, i.e. pipelines within Silon premises; this portion of the project has to be completed in September 2014.  Works will then be resumed in spring 2015 when  the heat distribution system in Silon s.r.o. premises will be renovated and the hot-water pipeline for heat supplies to the town of Sezimovo Ústí will be replaced.  The whole project is supposed to be completed in September 2015.

Outage 2014 - Due to the planned outage of the 110 kV substation operated by company E.ON, C-Energy Bohemia will have to completely interrupt its operation between 7th – 10th August 2014. During that time no energy will be produced.