March 16, 2014p3130061

CURRENT INFORMATON ABOUT PROJECTS EXECUTED BY C-ENERGY BOHEMIA S.R.O.

Ecologization and renovation of the heating plant in Planá nad Lužnicí

On 16th March 2014  the K3 boiler was put out of action as planned, and the following day its dismantling was launched. The boiler – a part of the key machinery in the plant - had been in operation for 46 years. After it is  dismantled and removed, it is to be replaced with a modern and ecological boiler K5 which is to be put into operation at the beginning of 2015. On Monday 17th March 2014 the reconstructed K4 boiler was taken over from the contractor for trial operation. K4 is not to be operated permanently, it will be used as a spare boiler. Gas motor-generators have been delivered to the site and currently the machinery building where the motor-generators will be operated is being built. At the same time the heat recovery steam generators and steel stands for pipelines are being constructed. More information about the project of the heating plant renovation is available in the  PROJECT PLANÁ section.  For photos from the construction site go to the Image Gallery.

Project funding: In the mid-March 2014 C-Energy Bohemia s.r.o. received another portion of the money from the subsidy granted from the European Funds (from the European Fund for Regional Development / Cohesion Fund) within the Operational Programme Environment, Priority Axis 2.