September 12 2013
CURRENT INFORMATION ABOUT PROJECTS EXECUTED BY C-ENERGY BOHEMIA S.R.O.
Ecologization and renovation of the heating plant in Planá nad Lužnicí: the general supplier „Corporation of PSG and Invelt Planá” took over the building site on Thursday 29 Aug. 2013. Construction works will be lunched in October by the construction of the foundations for the gas engine buliding.
Gas pipeline: STREICHER spol. s r.o. has been constructing the high-pressure gas pipeline which will bring gas to the C-Energy premises; the project is expected to be completed in December 2013.
Repair of the water distribution system: DAICH spol. s r.o. is finalizing works on the large-scale upgrade of water pipelines.
MISCELLANEOUS
C-Energy Bohemia s.r.o. has contributed a significant amount of money to the Tábor theatre for an upgrade of their admission ticket system. More info Social responsibility