May 17 2013110 kV substation

Current events in the project of general renovation of the Planá nad Lužnicí plant

- A contract was signed with company STREICHER  on the construction of a high-pressure gas pipeline to the plant premises. Works will be launched in July and the project is expected to be completed in December 2013.

- The replacement of the 110 kV cables is in progress. This project is planned to be compled in July 2013.

- At the end of April works on the renovation of the water distribution system started. After their completion in August 2013 the production of potable water in the water treatment plant in C-Energy Bohemia will be terminated and the industrial premises will be supplied from water mains operated by JVS.