March 26 2013
110 kV conduction
Current events in the project of general renovation of the Planá nad Lužnicí heating plant.
- Ground work is in progress in the C-Energy - Silon industrial premises. This is in preparation of the replacement of 110 kV cables which is supposed to be completed in July 2013.
- Repairs of the water distribution system in the industrial premises will be launched in April. After their completion in August 2013 the water treatment plant of C-Energy Bohemia will be closed down and companies on the premises will be supplied from the water mains operated by JVS.
- The building permit for the Planá Plant project (Ecologization and Renovation of the Planá Heating Plant) came into force on 21 March 2013